Forest Road Deactivation Practices
in the Pacific Northwest Navigation text
Navigation bar (text links below) Home Table of Contents section 01 section 02 section 03 section 04 section 05 section 06 section 07 section 08 section 09 section 10 section 11 section 12 section 13 section 14 section 15 section 17 section 17 section 18 section 19 section 20 section 21 section 22 section 23 section 24
17 - Cross-Ditching Practices Helpful Hints, Backup Cross-Ditches

Helpful Hints

Always excavate the cross-ditch from outlet to inlet. The cross-ditch inlet must be deeper than the base of the road ditch. Larger flows and steeper grades will require deeper cross-ditches. Armour outlet areas if erosion is expected. The size and placement of armour depends on anticipated flows and the risk to downstream values. Consider other means of erosion protection if rock is not readily available. Frequent cross-ditches can also be used to disperse hillslope drainage where unstable slopes exist below the road. Consciously choose safe locations for cross-ditches - never "just kick the water off the road". If access is to be maintained, carefully grade the approaches to allow for vehicle traffic. Remember a good rule of thumb: a cross-ditch should be at least five times wider as it is deep!

Always install the berm on the downgrade side of a cross-ditch, regardless of the direction of deactivation activities. To maintain or re-establish natural drainage patterns, cross-ditches should always be installed working downhill from the highest point.

Figure 16: Position of Berm
diagram: position of berm

If you anticipate erosion of the base of the cross-ditch, use armour to protect the base. In situations where frequent high flows are expected, but frequent vehicle access is required, consider the design and installation of fords and armoured swales.

Backup Cross-Ditches

17img

Backup cross-ditches are installed directly downgrade of the culvert location, unless otherwise instructed. Check with your supervisor in your access management plan if vehicle access must be maintained. Backup crossditches should be equal in size to the cross-sectional area at the highwater mark of the channel, and similar in design and shape to a regular crossditch. The height of ditch blocks at culverts and cross-ditches is important, and varies with the intended level of deactivation.

Install sediment control if water at the cross-ditch is flowing directly into fish habitat, or into a watercourse which is connected to fish habitat or a domestic water intake. Consider that you have the option to dewater channels to minimize the introduction of sediment into watercourses. Note the placement of armouring at the outlet of the above cross-ditch.


17 - Cross-Ditching Practices
 
Back Back Top of Page Top of Page
Home Home
Table of Contents Table of Contents  
Next Next
Introduction  1  section 01
Water Management  2  section 02
Revegetation  5  section 05
Sediment Control  6  section 06
section 13  13  Blanket Drains
section 14  14  Trench Drains
section 15  15  French Drains
section 16  16  Fords
section 13  17  Cross-Ditching Practices
section 24  24  Pre-Work Checklist
©1999 - 2002 Flip Productions Limited
Used with permission by CulvertBC