Forest Road Deactivation Practices
in the Pacific Northwest Navigation text
Navigation bar (text links below) Home Table of Contents section 01 section 02 section 03 section 04 section 05 section 06 section 07 section 08 section 09 section 10 section 11 section 12 section 13 section 14 section 15 section 16 section 17 section 18 section 19 section 20 section 21 section 22 section 23 section 24
8 - Dewatering Stream Channels Detailed Work Plan, Useful Hints

Dewatering streams is effective when removing culverts outside the fisheries windows, or in streams that present a high risk of sedimentation. Water can be pumped around the site with volume pumps, moved to below the working area by a gravity system or diverted away from the site in a temporary channel. Poorly planned and executed diversions can cause serious impacts on water quality and fish habitat, and can cause major erosion if "water is simply directed down the ditch for awhile ...". Supervisors and operators should prepare a detailed work plan and assemble all required tools and materials before work begins.

Diversion/Dewatering Work Plan

Develop and follow a step-by-step plan with the following points:

  1. Fish: isolate work site and remove fish from isolated section.
  2. Install downstream failsafe dam if deemed necessary.
  3. Install upstream diversion/dewatering works and initiate action.
  4. Complete planned instream deactivation work.
  5. Disassemble upstream works.
  6. Disassemble downstream works.
photo: water flow diversion
  1. Fish Removal is required before instream work begins. If the deactivation takes a full day, removal should take place the day before. Check with the agencies about timing of fish migration in the stream. The time period of the stream blockage should be minimized. Allow for fish passage if the project extends over several days.
  2. Building a Downstream Dam: the primary use of this structure is to catch minor sediment or suspended particles in the water. It also provides a level of comfort for unforeseen circumstances.
  3. Building an Upstream Dam: an effective dam is critical in any flow diversion as it must capture all the water flow. If you use a "pumparound", have a sufficient number of pumps (spares) and gas. Avoid using pumps if you can't complete the job in one shift.
  4. Complete the Instream Work as planned. Have ready and on site the water manager's tool kit to deal with the unexpected.
  5. Disassemble Upstream Dam but try to keep the dewater/diversion going as long as possible to facilitate the disassembly, and to minimize the release of a surge flow. Maintain the downstream works while the flows increase into the isolated stream section.
  6. Disassemble Downstream Dam only when water quality returns to normal levels. Remove the fish blockages and all materials and restore the site to its original state. Take pictures of the deactivated site for future inspections.

8 - Dewatering Stream Channels
 
Back Back Top of Page Top of Page
Home Home
Table of Contents Table of Contents  
Next Next
Introduction  1  section 01
Water Management  2  section 02
Revegetation  5  section 05
Sediment Control  6  section 06
Dewatering Streams  8  section 08
section 13  13  Blanket Drains
section 14  14  Trench Drains
section 15  15  French Drains
section 16  16  Fords
section 24  24  Pre-Work Checklist
©1999 - 2002 Flip Productions Limited
Used with permission by CulvertBC